23.4
Discovery, MGN, VMware Cloud and the 7 Rs
Planning with Application Discovery, rehosting with MGN, VM Import/Export, VMware Cloud on AWS, and the migration strategies.
22 min Reading + animations
Tip: tap or hover any dotted-underlined term to see what it means.
By the end of this lesson you will be able to
- Name the 7 Rs of migration (retire, retain, relocate, rehost, replatform, repurchase, refactor), say what each one changes, and match each to its AWS tool.
- Plan a data centre move with AWS Application Discovery Service: choose between the Agentless Collector and the Discovery Agent, find hidden dependencies, and group servers into applications and waves.
- Explain how AWS Application Migration Service (MGN) rehosts servers: replication agent, staging area, continuous block-level replication, test launch, cutover, finalize and archive, and what each step costs in downtime and money.
- Tell MGN from Elastic Disaster Recovery, VM Import/Export and VMware Cloud on AWS, and pick the right one from the keywords of a question.
- Use VM Import/Export to bring OVA, VMDK, VHD and raw images in as AMIs and send EC2 instances back out, and know its limits.
- Know the 2024–26 changes: Migration Hub and Application Discovery Service closed to new customers, AWS Transform, MGN’s new name, Amazon EVS, and Amazon Linux 2’s end of support, and which answer the exam still expects.
#Why moving servers needs a plan
Moving one server to AWS is easy. Moving a data centre is not: a Dhaka bank may run 300 servers, some nobody remembers, some that only work if another server is reachable, some with licences tied to old hardware. Moving them one by one, in the wrong order, breaks things on salary day.
So AWS describes a migration in three phases:
- Assess: what do we have, what would it cost in AWS, is it worth it? (A business case: Migration Evaluator, Application Discovery Service.)
- Mobilize: detailed discovery of servers and dependencies, a decision per application (the 7 Rs below), a landing zone (accounts, network, security), and a plan of waves: groups of applications that move together.
- Migrate and modernize: actually move each wave with the right tool (MGN for servers, DMS for databases in lesson 23.3, Snowball or DataSync for bulk data in lesson 23.5), then improve.
The exam asks about this in three ways: “which strategy” (the 7 Rs), “how do we plan” (Application Discovery Service), and “how do we move servers” (MGN, VM Import/Export, VMware Cloud on AWS). This lesson takes them in that order.
#The 7 Rs: seven ways to move an application
For every application, the team picks one of seven strategies. AWS’s list grew from Gartner’s 5 Rs to AWS’s 6 Rs, and then to 7 Rs when relocate was added. They are listed here from least to most change.
| R | Also called | What changes | Bangladesh example | Typical AWS tool |
|---|---|---|---|---|
| Retire | Decommission | The application is switched off and its data archived | A bank’s fax server for branch letters, unused for a year | None: archive to S3, switch off |
| Retain | Revisit | Nothing yet: it stays where it is, connected to what moves | Core banking on a vendor appliance not yet supported in any cloud | Hybrid links (VPN, Direct Connect) |
| Relocate | Hypervisor-level lift and shift | The platform’s location; VMs stay VMware VMs, operations unchanged | A bank’s 200 VMware VMs moved within weeks, still managed in vCenter | VMware Cloud on AWS (also: moving instances to another VPC, Region or account) |
| Rehost | Lift and shift | The hardware: same OS, same app, now on EC2 | A Chattogram garments ERP on old Windows servers, lease ends in three months | AWS Application Migration Service (MGN) |
| Replatform | Lift, tinker and shift | One part is swapped for a managed service; code stays | A Daraz-style shop moves its self-run MySQL to RDS; a Java app moves to Elastic Beanstalk | Amazon RDS, Elastic Beanstalk, containers |
| Repurchase | Drop and shop | The product: you buy SaaS instead of running your own | A software house drops its in-house leave and payroll app for a cloud payroll product | A SaaS product, often through AWS Marketplace |
| Refactor | Re-architect | The architecture: rebuilt with cloud-native services | A bKash-style wallet rebuilds payments as small services that scale on Eid eve | Lambda, ECS/EKS, DynamoDB, serverless |
The look-alikes the exam plays with:
- Rehost vs replatform. Rehost changes nothing in the server: MGN copies the whole disk, OS included. Replatform keeps the code but changes the platform under it: a managed database (RDS, lesson 7.1) instead of MySQL on a VM, or Elastic Beanstalk instead of a hand-built Tomcat server.
- Replatform vs refactor. Replatform is a small optimisation; refactor is a redesign (a monolith split into Lambda functions or ECS services). Refactor costs the most up front and is chosen when the business needs scale, agility or features the old design cannot give.
- Rehost vs relocate. Rehost turns each server into an EC2 instance. Relocate moves VMware VMs to VMware running on AWS: no conversion, the same vCenter, the same operations.
- Retire vs retain vs repurchase. Retire: nobody needs it. Retain: it is needed, but stays where it is for now. Repurchase: it is needed, but as somebody else’s SaaS.
Try it: each case below hides a look-alike. Pick an R first, then read why the other one is wrong.
7 Rs sorter: which R, which tool?
Read each case and pick the R you would choose. The answer, the AWS tool and the look-alike trap appear only after you pick.
A Chattogram garments factory runs its ERP on three old Windows servers. The data centre lease ends in three months and nobody has time to change a line of code.
Your answer
#Step 1: discover what you have
#Why discovery comes first
A migration plan built from an old spreadsheet goes wrong in three ways: a server nobody listed is left behind, a server is moved without something it depends on, and every server is given an EC2 instance as big as the old hardware even though it ran at 5% CPU. Discovery fixes all three with measured data.
AWS Application Discovery Service collects information about your on-premises servers so you can plan a migration:
- Configuration: hostname, OS, CPU count, memory, disks, IP and MAC addresses.
- Utilization: CPU, memory, disk and network use over time, so EC2 instances can be right-sized, not copied size for size.
- Dependencies: which processes run, and which server talks to which, on what port. This is the most important part for planning, because dependent servers must move in the same wave.
The data is stored encrypted in your home Region and shown in AWS Migration Hub, where you group servers into applications and plan waves. You can also export it (continuous export streams agent data to S3, where Athena can query it) or start from a CSV import of an existing inventory.
#Agentless Collector vs Discovery Agent
There are two ways to collect, and the difference is exactly what the exam tests:
| Agentless Collector | Discovery Agent | |
|---|---|---|
| What it is | One appliance VM (an OVA) deployed in your VMware environment, given read-only vCenter access | A small agent installed on each server (Windows or Linux, physical or virtual, any hypervisor) |
| Collects | VM inventory, configuration and performance history (CPU, memory, disk) of every VMware VM | Everything above plus running processes and the network connections between systems |
| Dependencies | Not from inside the VMs (newer versions add some network and database data collection) | Yes: the classic answer for a dependency map |
| Effort | Low: nothing on the servers | Higher: install and keep agents running on every server |
| Good for | A quick inventory and sizing of a large VMware estate | Physical servers, non-VMware hypervisors, and any plan that needs dependencies |
The older Agentless Discovery Connector in the slides was replaced by the Agentless Collector; since 17 November 2025 the service no longer accepts data from Discovery Connectors.
Application Discovery Service: what runs, and who talks to whom
A Dhaka bank plans to leave its data centre. Before moving anything it must know every server, how busy it is, and which servers depend on each other.
Scenario
One collector VM reads vCenter: inventory and utilization of every VMware VM, but no view inside them.
The team deploys the Agentless Collector, an appliance VM, into the bank’s VMware environment and gives it read-only vCenter credentials. Nothing is installed on the servers themselves.
#Step 2: rehost with AWS Application Migration Service (MGN)
#What MGN is
AWS Application Migration Service (MGN) is AWS’s main tool for rehost (lift-and-shift) migrations. It takes physical servers, virtual machines on any hypervisor (VMware, Hyper-V and others) and servers in other clouds and turns them into EC2 instances that boot natively on AWS, with no change to the application code. It supports a wide range of Windows and Linux versions and the databases and applications running on them (SAP, Oracle and SQL Server are common).
Its family tree matters for the exam:
- CloudEndure Migration: the company AWS bought in 2019; MGN is the “AWS evolution” of its replication technology.
- AWS Server Migration Service: the older, VM-only, snapshot-based tool. AWS discontinued it on 31 March 2022; MGN replaces it.
- AWS Transform MGN: since June 2026, the new name of the same service, reflecting its role as the replication engine behind AWS Transform. The console, the API and the
aws mgncommands are unchanged, and exam questions still say “Application Migration Service (MGN)”.
#How the replication works
- Install the AWS Replication Agent on each source server. It talks to the MGN service over TCP 443.
- MGN builds a staging area in a subnet you choose: a few small, cheap replication servers and low-cost EBS volumes, one per source disk. Full-size servers are not running; that is why replication is cheap.
- Initial sync: the agent copies every block of every disk to the replication servers over TCP 1500, encrypted in transit. The source server keeps working the whole time.
- Continuous block-level replication: after the initial sync, only changed blocks are sent, so the staging copy stays seconds behind the source.
- When you launch, MGN converts the disks so they boot on EC2 (drivers, boot loader, network) and creates the instance from your launch settings.
#Test, cutover, finalize
1. Set the launch settings
Each source server has an EC2 launch template (subnet, security groups, instance type, IAM role, tags; launch templates are explained in lesson 4.3) and MGN options such as right-sizing (pick an instance type from the source’s CPU and memory) and post-launch actions: Systems Manager documents that run on the new instance, for example installing the CloudWatch agent or removing old on-premises tools.
2. Launch test instances
A test launch creates EC2 instances from the latest replicated state while replication continues and the source keeps serving users. The team checks the application. If the test fails (wrong subnet, missing security group rule, a licence tied to the old hardware), fix it now: nothing is lost and no user noticed.
3. Mark ready, then cut over
After the test passes, the server is marked ready for cutover. In the cutover window: stop the application on the source, let the last blocks arrive, launch the cutover instance, switch DNS or the load balancer. Downtime is only this window, usually minutes.
4. Finalize and archive
When the new instance has run well for a while, finalize the cutover: replication stops and MGN deletes the staging resources, so their cost stops. Then mark the server as archived. Until you finalize, the untouched source is your rollback.
MGN: replicate, test, cut over
A Rajshahi university moves its exam-results server to EC2 with AWS Application Migration Service. Watch the blocks travel, and two ways a migration goes wrong.
Scenario
Agent, initial sync, continuous replication, a test launch, then a cutover of minutes.
The team installs the AWS Replication Agent on the results server. The agent registers with MGN over TCP 443, and MGN creates a staging area in the subnet the team chose.
The life of one source server in MGN
MGN tracks each server through fixed states. Follow a Chattogram garments ERP server from agent install to archive, and a cutover that has to roll back.
Scenario
Not ready → ready for testing → test → ready for cutover → cutover → finalize → archive.
The team installs the replication agent with a short-lived IAM credential. The server appears in MGN in the state Not ready while the initial sync runs.
#What MGN costs
Every source server gets 2,160 free hours of MGN, which is 90 days of continuous replication, counted from when the agent is installed. Most servers finish well within that. After that, MGN charges per server per hour of replication. Separate from the service fee, you always pay for the AWS resources it creates: the replication servers and staging EBS volumes, and the test and cutover EC2 instances and their volumes. Finalizing promptly is how you stop the staging cost.
#MGN or Elastic Disaster Recovery?
MGN and AWS Elastic Disaster Recovery (DRS) (lesson 23.2) are built on the same CloudEndure replication technology: an agent, a staging area, continuous block-level replication, launch on EC2. They do different jobs.
MGN: migrationDRS: disaster recovery
- Goal: move servers to AWS once, then switch off the source.
- Replication lasts weeks, until cutover; then it is finalized.
- Pricing: 90 days free per server, then per hour.
- Keywords: “lift and shift”, “rehost”, “migrate servers”.
- Goal: keep a recovery copy in AWS forever, launch it when disaster strikes, fail back later.
- Replication never ends; keeps point-in-time recovery snapshots.
- Pricing: per source server per hour, for as long as it is protected.
- Keywords: “disaster recovery”, “RPO of seconds”, “failback”.
The notes’ exam keyword “migrate physical/virtual servers to AWS for DR” mixes the two: migration → MGN, recovery → DRS.
#VM Import/Export
VM Import/Export moves virtual machine images between your virtualization environment and EC2, through S3. It is a free feature; you pay only for the S3 storage and the EBS snapshots and instances it creates.
Import (ec2 import-image, or import-snapshot for a single disk):
- Accepted formats: OVA (a whole VM, can hold several disks), stream-optimized VMDK (VMware vSphere), VHD and VHDX (Hyper-V, also Azure and Citrix Xen) and raw images.
- Flow: export the VM from your hypervisor → upload the file to S3 → call import-image with a service role named vmimport that may read the bucket → the service converts it → you get an AMI (or an EBS snapshot) and launch instances from it (AMIs, lesson 4.3).
- Limits: only operating systems on the supported list (most Windows Server and Linux versions); no VMs created by physical-to-virtual conversion; no Arm-based images.
Export (ec2 create-instance-export-task, or export an AMI):
- Output formats: OVA, VMDK or VHD, written to an S3 bucket in the same account (SSE-S3 or unencrypted; not SSE-KMS).
- You cannot export an instance that contains AWS-provided third-party software (Windows or SQL Server from AWS AMIs, Marketplace images), one with encrypted EBS snapshots, more than one disk or more than one network interface, or volumes over 1 TiB.
When to use it rather than MGN: a one-off image (a vendor appliance shipped as an OVA, a golden VM built on premises), a DR repository of VM images kept in AWS (see the slides’ use case), or taking a workload back on premises. When the servers are live, numerous, physical, or must keep running until cutover, use MGN.
VM Import/Export: disk images in, disk images out
A Sylhet software house has a ready-made VMware image of its billing appliance. VM Import/Export turns it into an AMI through S3, and can send EC2 instances back out as images.
Scenario
Export from VMware, upload to S3, import-image converts it into an AMI.
The admin exports the VM from vCenter as an OVA file. VM Import accepts OVA, stream-optimized VMDK, VHD or VHDX, and raw images.
#VMware Cloud on AWS
#What it is
Many companies have run VMware for years: vSphere (the hypervisor and its hosts), vCenter (management), vSAN (storage) and NSX (networking), and their IT team knows these tools well. VMware Cloud on AWS runs that same VMware stack, as a software-defined data center (SDDC), on dedicated AWS bare-metal hosts in an AWS Region. VMware (now Broadcom) operates the stack; AWS provides the hardware.
- Same tools, no retraining. The team manages the SDDC with the same vCenter, often linked to the on-premises one.
- No conversion. VMs move as VMware VMs. With VMware HCX they can move live with vMotion (no reboot, same IP address on a stretched network) or in bulk (replicate, then reboot once at a planned time).
- AWS services next door. The SDDC is connected to a VPC in your own account, so VMs can use S3, RDS, FSx, Redshift and other services privately (FSx already lists VMware Cloud on AWS as a client, lesson 12.2).
Use cases, in the slides’ order: migrate vSphere workloads to AWS (this is the relocate R), extend a data centre and run production across private and public VMware clouds (hybrid), and keep a disaster recovery site on AWS.
VMware Cloud on AWS: same vCenter, new data centre
A bank’s 200 VMware VMs move to a VMware environment that runs on AWS bare metal. The team keeps vCenter and vMotion; AWS services sit next door.
Scenario
A running VM moves to the SDDC with no reboot; the team never leaves vCenter.
The bank subscribes to VMware Cloud on AWS. An SDDC is built on dedicated AWS bare-metal hosts with the same stack the bank runs today: vSphere, vCenter, vSAN storage and NSX networking.
#Choosing the tool from the question
| The question says… | Answer | Lesson |
|---|---|---|
| Plan the migration, utilization, dependencies between servers | Application Discovery Service (Discovery Agent for dependencies) | here |
| Business case, TCO before deciding | Migration Evaluator | here |
| Lift and shift hundreds of physical servers and VMs, minimal downtime | MGN | here |
| Import a VM image (OVA, VMDK, VHD) as an AMI, export back on premises | VM Import/Export | here |
| Keep vCenter and vSphere, no retraining, VMware DR | VMware Cloud on AWS | here |
| Continuous replication for disaster recovery, failback | Elastic Disaster Recovery | 23.2 |
| Move a database, keep it in sync, change engine | DMS (plus SCT for a different engine) | 23.3 |
| Hundreds of TB, “would take months over the internet” | Snowball (offline), or DataSync over Direct Connect | 23.5 |
| File shares and backups stay on premises, cached in AWS | Storage Gateway | 12.3 |
A typical full answer combines them: discover with Application Discovery Service, rehost the application servers with MGN, move the database with DMS, ship the file archive on Snowball, and connect the sites with Site-to-Site VPN or Direct Connect while the waves run.
#What goes wrong
- Hidden dependencies. A server moved without one it calls (an SMS gateway, a licence server, a file share) fails in production. Run Discovery Agents long enough to see monthly and quarterly jobs, then move dependent servers in the same wave.
- Sizing copied, not measured. Old 32-core hosts copied to 32-vCPU instances waste money. Use utilization data and MGN right-sizing, then adjust after cutover.
- Wrong launch settings. A default launch template puts the instance in the wrong subnet or security group; the test launch catches it. Never skip the test.
- Replication lag at cutover. A slow or shared link, or a source that writes faster than the link carries, keeps lag high, so the cutover window grows. Sync weeks ahead, add bandwidth (VPN or Direct Connect), cut over on a quiet day.
- Licences and hardware ties. Software licensed to a MAC address, a dongle or a host ID may refuse to start on EC2. Check with the vendor before cutover; consider Dedicated Hosts for bring-your-own-licence rules.
- Forgetting to finalize. Staging servers and volumes keep costing money after cutover until you finalize, and the 90 free days of MGN run out for servers left replicating.
- Wrong tool. VM Import for physical servers (not supported), VMware Cloud on AWS for Hyper-V (needs VMware), DRS for a one-time migration (it is for recovery), Server Migration Service in a new design (discontinued).
#Try it yourself
These commands use AWS CLI v2. The account, IDs and names are examples. MGN must be initialized in the Region once (from the console) before the aws mgn commands work.
# 1. Application Discovery Service: see the agents and start collecting
aws discovery describe-agents --region ap-southeast-1
# { "agentsInfo": [ { "agentId": "o-0123456789abcdef0", "hostName": "payroll-app",
# "agentType": "EC2", "health": "HEALTHY", "collectionStatus": "STOPPED" }, ... ] }
aws discovery start-data-collection-by-agent-ids --agent-ids o-0123456789abcdef0
aws discovery start-continuous-export # agent data streams to S3, ready for Athena
# { "exportId": "export-1234567890abcdef0", "s3Bucket": "aws-application-discovery-service-111122223333-example",
# "dataSource": "AGENT", "startTime": "2026-11-01T10:00:00Z" }
# 2. MGN: list source servers and their lifecycle state
aws mgn describe-source-servers --region ap-southeast-1 \
--query 'items[].{id:sourceServerID,host:sourceProperties.identificationHints.hostname,state:lifeCycle.state}'
# [ { "id": "s-1234567890abcdef0", "host": "results-01", "state": "READY_FOR_TEST" } ]
# 3. Launch a test instance, then mark the server ready for cutover once the test passes
aws mgn start-test --source-server-ids s-1234567890abcdef0
aws mgn change-server-life-cycle-state --source-server-id s-1234567890abcdef0 \
--life-cycle state=READY_FOR_CUTOVER
# 4. Cut over, then (after a quiet week) finalize and archive
aws mgn start-cutover --source-server-ids s-1234567890abcdef0
aws mgn finalize-cutover --source-server-id s-1234567890abcdef0
aws mgn mark-as-archived --source-server-id s-1234567890abcdef0
# 5. VM Import: bring an OVA from S3 in as an AMI and watch the task
aws ec2 import-image --description "billing appliance" \
--disk-containers '[{"Format":"ova","UserBucket":{"S3Bucket":"vm-images-example","S3Key":"billing.ova"}}]'
# { "ImportTaskId": "import-ami-0123456789abcdef0", "Status": "active", "Progress": "1" }
aws ec2 describe-import-image-tasks --import-task-ids import-ami-0123456789abcdef0 \
--query 'ImportImageTasks[0].[Status,StatusMessage,ImageId]'
# [ "completed", null, "ami-0abcd1234example" ]
# 6. VM Export: send an imported instance back out as an OVA
aws ec2 create-instance-export-task --instance-id i-0abcd1234example --target-environment vmware \
--export-to-s3-task DiskImageFormat=VMDK,ContainerFormat=ova,S3Bucket=vm-images-example,S3Prefix=exports/
# { "ExportTask": { "ExportTaskId": "export-i-0123456789abcdef0", "State": "active" } }
Remember to finalize or disconnect test servers in MGN and delete test AMIs and snapshots when you finish, or the staging resources keep billing.
#Summary
Key takeaways
- The 7 Rs: retire (switch off), retain (keep for now), relocate (VMware to VMware Cloud on AWS), rehost (lift and shift with MGN), replatform (swap a part for RDS or Beanstalk), repurchase (buy SaaS), refactor (rebuild cloud-native).
- Application Discovery Service plans the move: configuration, utilization and, with the Discovery Agent, processes and network dependencies; the Agentless Collector gives VMware inventory and performance without agents. Results are grouped in Migration Hub.
- MGN rehosts physical, virtual and cloud servers to EC2: agent → staging area (cheap replication servers and EBS) → continuous block-level replication → test → cutover (minutes of downtime) → finalize → archive. 90 days free per server; staging and instances are billed.
- MGN replaced CloudEndure Migration and Server Migration Service (discontinued March 2022); since June 2026 it is also called AWS Transform MGN. MGN migrates, DRS protects: same technology, different job.
- VM Import/Export turns OVA, VMDK, VHD/VHDX and raw images in S3 into AMIs, and exports instances as OVA, VMDK or VHD; no physical-to-virtual images, no export of AWS-licensed Windows.
- VMware Cloud on AWS keeps vCenter, vSphere, vSAN and NSX on AWS bare metal, moves VMs live with HCX and vMotion, and is the answer for “keep VMware tools, no retraining”. AWS stopped reselling it in 2024; Amazon EVS (2025) runs VMware Cloud Foundation in your VPC.
- Since November 2025, Migration Hub and Application Discovery Service are closed to new customers, with AWS Transform as the successor; the exam answer for discovery is still Application Discovery Service.
Answer on your own first, then read the explanation, even when you got it right.
Self-checkQuestion
A company wants to plan the migration of its data centre and must first understand which on-premises servers communicate with each other. Which service fits?
Self-checkQuestion
Which strategy moves an application to EC2 without any change to its code or operating system?
Self-checkQuestion
What is the main cost advantage of the MGN staging area while replication runs?
Self-checkQuestion
How much MGN service time is free for each source server?
Self-checkQuestion
Which two items can the Discovery Agent collect that the Agentless Collector cannot gather from inside the VMs?
Choose 2
Self-checkQuestion
A bank runs 200 VMs on VMware. Its team knows vCenter well and the board wants to leave the data centre within weeks without converting VMs or retraining staff. What should the architect recommend?
Self-checkQuestion
A university has 40 servers: some on Hyper-V, some physical. It wants them on EC2 with minimal change and only minutes of downtime per server. Which approach fits best?
Self-checkQuestion
During an MGN migration the test launch fails because the instance cannot reach the database. What is the right next step?
Self-checkQuestion
Which statement about downtime with MGN is correct?
Self-checkQuestion
A company’s application is no longer used by anyone and costs money to keep running. Which R applies?
Self-checkQuestion
An online shop moves its application unchanged but replaces its self-managed MySQL server with Amazon RDS to stop patching it. Which strategy is this?
Self-checkQuestion
Which two statements about MGN and AWS Elastic Disaster Recovery are correct?
Choose 2
Self-checkQuestion
An old practice question offers AWS Server Migration Service for a new server migration project in 2026. What should you answer in practice?
Self-checkQuestion
Which formats can VM Import/Export import as an AMI?
Self-checkQuestion
An admin tries to export an EC2 instance that was launched from an AWS-provided Windows Server AMI back to VMware. The task fails. Why?
Self-checkQuestion
Which two are valid uses of VM Import/Export?
Choose 2
Self-checkQuestion
A team ran only the Agentless Collector, planned waves from its data, and after moving a payroll app found that it could no longer reach an SMS gateway left on premises. What should they have done?
Self-checkQuestion
Where is Application Discovery Service data viewed and grouped into applications for wave planning?
Self-checkQuestion
A company plans to move a monolithic wallet application to microservices on AWS Lambda and DynamoDB so it scales on peak days. Which R is this?
Self-checkQuestion
Which two statements about VMware Cloud on AWS are correct?
Choose 2
Self-checkQuestion
During a vMotion from on premises to VMware Cloud on AWS, the network link drops halfway. What happens to the VM?
Self-checkQuestion
A team finished cutover for 50 servers in MGN two months ago but never finalized. What is the consequence?
Self-checkQuestion
The ERP fails at cutover because its licence is tied to the old server’s MAC address. The source has not been finalized. What is the fastest safe recovery?
Self-checkQuestion
A source server has 4 TB of disks and a dedicated 100 Mbps link at full speed. About how long does MGN’s initial sync take?
Self-checkQuestion
Which two are part of MGN launch settings?
Choose 2
Self-checkQuestion
An architect must give management a cost comparison of staying on premises versus moving to AWS before any migration is approved. Which tool builds this business case?
Self-checkQuestion
A company replaces its own on-premises CRM with a subscription SaaS CRM and moves only the customer data. Which R is this?
Self-checkQuestion
The notes say Amazon Linux 2 can be downloaded as an .iso to run on premises. What is accurate in late 2026?
Self-checkQuestion
Which statement about AWS’s migration tooling in 2025–26 is correct?
Self-checkQuestion
A company must move hundreds of servers, a 20 TB Oracle database and a 300 TB file archive to AWS, with dependency data first. Which combination is the best fit?